Aerial view from May 2026 of the flat white roofs of the existing South Shore Tech buildings beside a newly paved parking lot, with construction fencing, piles of soil and a cleared work area at the edge of the woods
South Shore Tech building project

The South Shore Regional Vocational School Committee and the South Shore Tech building committee meet together Wednesday, Nov. 18, to vote on another month of bills, a set of contract awards and a change order for the new $276 million school in Hanover, and the superintendent is set to brief members on the district's fiscal 2028 budget.

The new building is going up on the school's Webster Street campus while students keep using the old one. It is designed for 900 students in grades 9 to 12, and it makes room for new plumbing and veterinary science programs, which the district says a renovation of the current building could not have fit without closing other programs. The nine member towns, Abington, Cohasset, Hanover, Hanson, Marshfield, Norwell, Rockland, Scituate and Whitman, carry the local share of the cost.

When and where

The School Committee and its Negotiations Subcommittee meet first, at 5 p.m., and the agenda calls for them to go straight into a closed executive session on collective bargaining for the district's Units A and B. The joint meeting of the School Committee and the School Building Committee follows at 6 p.m. Both notices, posted Nov. 13, list the address as 436 Webster St., Hanover, but the school is at 476 Webster St., and the joint meetings of July 22, Aug. 19 and Sept. 9 were held there, in the school's Brass Lantern. Each committee has its own public comment period on the 6 p.m. agenda.

What is on the agenda

For the School Committee, the agenda lists administrator reports, a presentation from Unibank under old business, approval of the Oct. 14 minutes, the treasurer's monthly report and a fiscal 2028 budget update from the superintendent-director. Members are also asked to accept a donation of a 2002 Audi TT convertible, valued at about $4,700, for the automotive program.

The building committee is set to vote on monthly invoices from LeftField, the owner's project manager; Drummey Rosane Anderson, the architect; Suffolk Construction, the construction manager; and UTS, the testing firm. It also faces votes on recommended contract awards, an amendment to the UTS testing contract and a change order the agenda describes as carrying no additional cost, followed by updates from the project manager, the designer and the construction manager. The night closes with a School Committee executive session on litigation strategy and the Unit A and B talks.

The money

The project's total budget is $276,449,480, contingencies included. The Massachusetts School Building Authority's board approved a grant of up to $109,641,623 on Oct. 30, 2024, and voters in the nine towns approved the project in a single combined election on Jan. 25, 2025, which the district says passed by 78%.

Through Aug. 31, the project had spent $29,475,826 and had committed $95,246,003, about 34% of the budget, according to the August report from LeftField, the owner's project manager, the most recent monthly report the district has posted. August alone accounted for $3,323,743 of that spending, including a $2,869,977 payment request from Suffolk. The $11,180,190 construction contingency and the $1,118,019 owner's contingency were both untouched at the end of August.

The district estimates it will finance about $162 million after stabilization funds and equipment grants are applied, with the rest of the cost paid through municipal bonds over 20 to 30 years. Its projections assume interest-only short-term borrowing in fiscal 2026 through fiscal 2028 and bonds starting in fiscal 2029, though the first bonds could wait until fiscal 2030, and no borrowing decision is made until the district is ready to bond. It has said it would consult with the towns before any bonding decisions for fiscal 2029 and later. Under the cost agreement among the nine towns, each town's share of the debt follows its student enrollment on a four-year rolling average, with its percentage of the district's students in fiscal 2025 as the base.

Residents can see what the project means for their own tax bill on the district's tax impact page, which has a projection sheet and an explainer video for each of the nine towns. The sheets compare level debt payments with level principal payments and show a projected fiscal 2029 tax rate increase under each, and Abington also posts a calculator on its town website for estimating a single home's bill. Questions about the tax estimates go to Superintendent Thomas Hickey at thickey@ssvotech.org or district Treasurer James Coughlin at jcoughlin@ssvotech.org.

The schedule

Site work began in April 2026, and foundations started Aug. 17. The August report said Suffolk was aiming to have the final guaranteed maximum price, the ceiling on the construction contract, compiled in October, and the schedule attached to that report gave Oct. 26 as the finish date for signing it.

Under the construction manager's schedule in the same report, the new building reaches substantial completion June 8, 2028. Students finish the 2027-28 year in the old school, with the last day of classes listed as June 20, 2028, and the first day of classes in the new building as Aug. 30, 2028. The owner's project manager's schedule lists the opening as Sept. 1, 2028. Demolition of the old school and construction of new fields and parking would follow, running from July 2028 to Aug. 24, 2029.

Who is in charge

Dustin Reardon of Norwell chairs the nine-member School Committee, with Joseph Zambello of Marshfield as vice chair and Coughlin, the treasurer, as its secretary. The August report lists Bob Heywood as the building committee's representative.

Past joint meetings are posted on video on the district's School Committee page, and questions about the building project go to info@southshoretechproject.com.