Reported by us | Hanover

South Shore Tech approves seven subcontracts worth $10.6 million for its new Hanover school

Demolition, kitchen equipment and a wastewater treatment facility lead the list, and the superintendent-director says the $276 million project remains on budget and on schedule to open in 2028.

By the South Shore 360 Schools Desk | Published Nov. 20, 2026 | Last verified Nov. 20, 2026, 2:21 p.m. ET

HANOVER, Mass. The South Shore Tech building committee approved seven subcontracts worth a combined $10.6 million Wednesday for the new vocational school going up in Hanover, Superintendent-Director Thomas Hickey said Friday.

The awards, made at the Nov. 18 joint meeting of the South Shore Regional Vocational School Committee and the School Building Committee, let Suffolk Construction, the project's construction manager, sign contracts with firms for metal panels, food service equipment, carpet, demolition, spray booths, resinous flooring and a wastewater treatment facility. Hickey laid out the awards, a no-cost change order and a larger testing contract in an email answering questions from South Shore 360, and said the $276,449,480 project "remains on budget and on schedule to open for school year 2028."

The new building, designed for 900 students in grades 9 to 12, is rising on the school's Webster Street campus while students keep using the old one. The Massachusetts School Building Authority approved a state grant of up to $109.6 million for it in October 2024, and the district's nine member towns carry the local share: Abington, Cohasset, Hanover, Hanson, Marshfield, Norwell, Rockland, Scituate and Whitman, with each town's share of the debt following its enrollment at the school.

The seven contracts

AwardWorkFirmAmount
RTA #29Metal panelsSunrise Erectors, Inc.$1,614,896
RTA #30Food service equipmentTrimark United East$2,103,000
RTA #31CarpetBusiness Interiors Floor Covering$337,000
RTA #32DemolitionJDC Demo & Abatement LLC$3,707,860
RTA #33Spray boothsCollision Center Design LLC$318,650
RTA #34Resinous flooringSelect Tile, Marble & Flooring$410,000
RTA #35Wastewater treatment facilityPride Environmental & Const., Inc.$2,130,000
Total$10,621,406

The amounts are as Hickey listed them, and South Shore 360 added the total. RTA stands for recommendation to award. Demolition is the largest award at $3.7 million, followed by the wastewater treatment facility and the kitchen equipment at about $2.1 million each. The district's October project report, posted this month, said awards for six of those trades would go to the building committee in November, and Suffolk's report in the same document said about 82% of the project's work had been bought out, the construction term for trades placed under contract. That buyout happens inside Suffolk's $215,154,134 construction contract, which the October budget report already counts in full as money committed.

A change order with no added cost

Hickey said the change order on Wednesday's agenda, which carried no added cost, let Suffolk move money already set aside in the contract's allowances to pay for supports for the roof screens, a new location for a planned fire hydrant, a second added hydrant, a water sampling unit and a WES system, a wireless evacuation and alarm system to be used during construction. "The latter 4 items resulted from collaboration with the Town of Hanover Fire and Water Departments," he wrote.

Suffolk's October change log lists those five items at $225,000 for the roof screen support steel, $14,916 for the hydrant's new location, $27,526 for the added hydrant, $24,874 for the water sampling unit and $38,377 for the evacuation system, $330,693 in all, each paid from an allowance inside the contract. The same report shows the construction contract at $215,154,134 at the end of October, with no change orders adding to it.

The amendment to the contract with UTS, the project's testing firm, "increases our contract allowance for 3rd party construction testing for soils, concrete, and structural elements to verify our contractors are building and meeting the required specifications," Hickey wrote. The project budget sets aside $400,000 for testing services, and through Oct. 31 the project had committed $100,000 of it and spent $81,495, according to the October budget report.

The price and the schedule

The building committee approved the final guaranteed maximum price, the ceiling on Suffolk's construction contract, at its Oct. 14 meeting, Hickey said. "The total value of the GMP is $215,154,134.00 which was $8.5M under the budget for construction," he wrote, adding that "the bid savings will be transferred to the Owner's Contingency." The October budget report lists the construction budget at $223,603,801, which is $8,449,667 above the contract price, and Suffolk's report says the final price was signed Oct. 15.

Through Oct. 31, the project had committed $244,832,055, about 89% of its total budget, and had spent $41,446,523, a figure that counts October's bills, including Suffolk's eighth payment request of $7,910,277.62. The $11,180,190 construction contingency and the $1,118,019 owner's contingency had not been touched, and the Oct. 31 report does not yet show the bid savings moved into the owner's contingency.

The construction update on the project's website scheduled precast panel erection to begin Nov. 9, the last foundations to be finished in December and structural steel erection to begin in January 2027, a month later than the October report's summary listed. The project schedule calls for the new building to be substantially complete June 8, 2028, and for the first day of classes there to be Aug. 30, 2028, after which the old school comes down and new fields and parking are built, with the whole project done Aug. 24, 2029.

Next year's budget

Hickey said he told the School Committee the fiscal 2028 budget process is underway and gave no specific presentation. Departments typically submit their requests by early November, he wrote, and he plans a high-level presentation in December and a more detailed one in January. Budgets are typically certified after the governor's proposed state budget comes out by the end of January, he said.

"The main fixed cost drivers for the budget are similar across all towns and districts: inflation, health insurance, and Plymouth County retirement," Hickey wrote. He said the district will also look to hire teachers for its new veterinary tech and plumbing programs later in the 2027-28 school year, to prepare for the new building's opening in 2028-29.

A video of Wednesday's meeting had not been posted to the district's YouTube channel as of Friday afternoon, and Hickey said he would check on when it will be posted to the district's website. Questions about the building project go to info@southshoretechproject.com. The project's site posts the monthly reports and each town's December 2024 tax impact estimate, and it lists the two committees' next joint meeting for December, the month Hickey plans his high-level presentation on next year's budget.

Label: Reported by us.

Corrections

No corrections to this story. If something here is wrong, tell us. Every correction is dated on the story and listed in our public log.

Sources (10)

  1. Email from Superintendent-Director Thomas Hickey, South Shore Regional Vocational Technical High School, to South Shore 360, Nov. 20, 2026, 1:49 p.m., answering our Nov. 19 questions (no web copy)
  2. Joint meeting of the South Shore Regional Vocational School Committee and School Building Committee, agenda for Nov. 18, 2026, posted Nov. 13
  3. LeftField, OPM Monthly Project Update Report, October 2026, with the Total Project Budget Status Report dated Oct. 31, 2026, and Suffolk Construction's October 2026 monthly report, South Shore Tech building project, read Nov. 20, 2026
  4. South Shore Tech building project, joint meeting event page for Nov. 18, 2026
  5. South Shore Tech building project, home page with the construction update, document library and estimated tax impacts pages, read Nov. 19 and 20, 2026
  6. South Shore Tech, YouTube channel, read Nov. 20, 2026
  7. South Shore Tech, "Press Release for Schematic Design", read Nov. 20, 2026
  8. Town of Abington, SSVT Building Project page
  9. Massachusetts School Building Authority, "New South Shore Regional Voc Tech High School Approved," Oct. 30, 2024
  10. South Shore 360, "South Shore Tech committees meet Wednesday on the $276 million new school and next year's budget," Nov. 16, 2026

This story on the full site